Permit to Conduct Building Work Out of Hours - City of Port Phillip - Victoria

Description

You may require this permit if you intend to carry out building activities outside of normal business hours, which are typically 7:00am - 6:00pm weekdays. Please consult the council for more information regarding normal work hours on weekends.

Types of activities may include:

  • conducting works
  • activities, events or practices connected with construction
  • demolition or removal of a building or temporary structure (such as fences, outbuildings, masts, poles, etc).

Service type

Licence

A licence defines the need to obtain recognition / certification and registration to undertake a certain business activity.

Duration

As specified on the permit.

Fees

Fees Details for this service in table format.

Task Type Business Structure Amount Description
Apply Application All $125.00

Out of hours application for works undertaken outside approved hour. You will also be required to pay a licence fee. Fees for 2024-25

Apply Licence All $455.00

Works undertaken outside approved hours per day. Fees for 2024-25

Act(s) name

Local Government Act 2020 Victoria

Administering agency

City of Port Phillip

Contact details

Contact Email, Phone and Address Details for this service in simple two column table format, header then data.